JUNE 2003
Pictures before remodel, site prep



JULY 2003
Site prep, lift house, temp power, footing and foundation

AUGUST 2003
Finish forms, pour concrete, install water tank for fire safety

SEPTEMBER 2003
Frame lower story, demo half of house, frame floor, lay pipe, backfill

OCTOBER 2003
Frame walls, frame loft, install sheer ply, ridge beam, rafters and posts

NOVEMBER 2003
Framing, sheer ply, roofing, cut out windows, dig drains, set DI box and pipe

DECEMBER 2003
Set windows and sliders, trim, siding, deck footings and foundation, pour garage slab

JANUARY 2004
Sheetrock, insulate and plywood roof, set skylights, build porch, electrical and plumbing, siding

FEBRUARY 2004
Final prep for roofing, siding, trim out, finish closing in remodel